Construction projects are basically bound by a contract document. The document regulates the duration of the project, the scope of the project and the specifications of the project as well as the rights and obligations of each party between the contractor and the owner. With this contract, it is expected that the construction project can run smoothly and on time. However, claims are still often submitted in the construction process. Therefore, a study was conducted to determine the factors causing claims made by the contractor to the owner. Using a quantitative descriptive approach method, the results showed that the factors that dominate the submission of contractor claims are the owner's delay in approving shop drawings with an Importance Index of 0.871. There were design changes made by the owner with an Importance Index of 0.842. The occurrence of high rainfall intensity with an Importance Index of 0.751. The requested material is not available in the city but must be indented with an Importance Index of 0.743. There is additional work outside the contract specified by the Importance Index of 0.729.

Downloads

Download data is not yet available.

References

Ariani, V., “Identifikasi Penyebab Timbulnya Pengajuan Klaim Konstruksi Dari Penyedia Jasa Ke Pengguna Jasa Di Kota Padang”, Jurnal REKAYASA, P-ISSN: 1412-0151 E-ISSN:2622-9455, 2022.

Dharma, P., “Analisis Pengukuran Relative Importance Indek (RII) untuk menentukan Peringkat Faktor Penyebab Keterlambatan Pekerjaan Kanopi Proyek East Connection Taxiway Bandara Soekarno-Hatta”, Contruction and Material Journal, p-ISSN: 2964-4437, e-ISSN: 2808-2869, 2023.

Ghozali, I., Aplikasi Analisis multivariete dengan program IBM SPSS 23 (Edisi 8). Semarang: Badan Penerbit Universitas Diponegoro, 2016.

Herry, P., “Studi Tentang Pengajuan Klaim Konstruksi Dari Kontraktor Ke Pemilik Bangunan”. Civil Engineering Dimension. ISSN 1410-9530, 2005.

Hubertha, C., “Faktor Penyebab Klaim Pada Proyek Infrastruktur Sanitasi Berdasarkan FIDIC MDB Harmonised Edition 2010”, Jurnal Konstruksia, p-ISSN : 2086-7352, e-ISSN : 2443-308X, 2023.

Nurisra, “Faktor Penyebab Pengajuan Klaim Pada Proyek Konstruksi di Banda Aceh”, Jurnal Teknik Sipil, pp. 93-99, 2009.

Pusdiklat Kementerian Pekerjaan Umum dan Perumahan Rakyat, Analisis Penyelesaian Sengketa Kontrak Konstruksi, Bandung, 2017.

Resy, Y., “Analisa Faktor Penyebab Klaim Pada Proyek Konstruksi Dengan Kontrak Design And Build Terhadap Kinerja Biaya dan Waktu”, Seminar Nasional Pascasarjana, Depok, 2019.

Sarwono, J., Metode Riset Skripsi Pendekatan Kuantitatif (Menggunakan Prosedur SPSS): Tuntunan Praktis dalam Menyusun Skripsi, Jakarta : Elex Media Komputindo, 2012.

Sugiyono, S., Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Bandung: Alfabeta, 2017.

Yeremi J., “Kajian Penyebab Klaim Konstruksi di Negara Berkembang – Studi Kasus: Indonesia, Uni Emirate Arab, & India”, Journal of Sustainable Construction, p-ISSN: 2964-4437, e-ISSN: 2808-2869, 2023.

Z. Z. Noor, Metodologi Penelitian Kualitatif dan Kuantitatif, Jakarta: Kencana, 2020.

Downloads

Published

2025-03-31

How to Cite

lilis novitasari, Fetriani, M., & Natalia, M. (2025). Analysis of Contractor’s Construction Claim Submission. CIVED, 12(1), 341–347. https://doi.org/10.24036/cived.v12i1.753

Issue

Section

Articles