Comparative Analysis of Crawler Crane Productivity in Girder Erection: A Theoretical Study and Direct Observation
DOI:
https://doi.org/10.24036/cived.v12i1.698Keywords:
Heavy Equipment, Erection Girder, Cycle Time, ProductivityAbstract
Every construction project, in general, has a specific and systematic method implementation program, such as the utilization of heavy equipment in girder erection work. This focus is selected based on the high technical complexity of girder erection work, so the productivity of heavy equipment greatly affects the work's success. The aim is to analyze the suitability between theoretical calculation of crawler crane productivity and direct observations in girder erection work and identify the factors that cause the productivity difference. This study combines the theoretical calculations and direct observations to evaluate the productivity of crawler cranes in girder erection work. Based on theory, the method of calculating crane productivity is done by analyzing the operating cycle time and productivity of crawler cranes. With the direct observations method, actual data is taken in the field, which is then calculated as the result of its productivity. From the results of this study, it is found that the results of crawler crane productivity in direct observation in the field have a higher productivity value compared to the productivity value in theoretical calculations, namely 1.51 units/hour, while in theoretical calculations, the productivity value is 1.060 units/hour. The difference in value is caused by several factors in the field, such as weather conditions, operational obstacles, and the operator's efficiency.
Downloads
References
J. N’Cho, "Contribution of talent analytics in change management within project management organizations The case of the French aerospace sector," Procedia computer science, vol. 121, pp. 625-629, 2017, doi: https://doi.org/10.1016/j.procs.2017.11.082.
A. Nursin, F. Fitria, and T. W. Sari, "Last Planner System pada Proyek Rumah Susun Transit Oriented Development," in Prosiding Seminar Nasional Teknik Sipil, 2020, pp. 32-40. [Online]. Available:https://prosiding-old.pnj.ac.id/index.php/snts/article/download/3612/2038?__cf_chl_tk=YwJ8VDZUmMYEOGDySnLtQSk7btcYqadsrShaUVxaBi0-1735009117-1.0.1.1-8af8ylPgvvfTfFKwZxB.QjeS7OAFapkT0PEUsbg7F_0.
B. B. Kalengkongan, T. T. Arsjad, and J. B. Mangare, "Analisa Perhitungan Produktivitas Alat Berat Pada Pekerjaan Pematangan Lahan Pembangunan Tower Sutet Likupang-Paniki," Jurnal Sipil Statik, vol. 8, no. 1, 2020. [Online]. Available: https://ejournal.unsrat.ac.id/index.php/jss/article/view/27722/0.
A. Setiobudi, "Pengujian Kuat Tekan Beton Mutu Tinggi Type Fc’ 50 (Kelas Aa) Untuk Girder Jembatan Di Tol Palembang Indralaya (Palindra)," Jurnal Deformasi, vol. 2, no. 1, pp. 7-25, 2017, doi: https://doi.org/10.31851/deformasi.v2i1.1200.
D. Wijanarko and R. W. Rahmadi, "Optimalisasi Produksi Alat Berat Dalam Pekerjaan Galian Dan Tanaman Di Proyek Jalan Raya (Studi Kasus: Jalur Lintas Selatan Lot 2 Blitar)," Jurnal Daktilitas, vol. 4, no. 01, pp. 25-36, 2024. [Online]. Available: https://journal.unita.ac.id/index.php/daktilitas/article/view/1157/669.
S. S. Chandra, S. M. Sepasgozar, V. R. P. Kumar, A. K. Singh, L. Krishnaraj, and B. O. Awuzie, "Assessing factors affecting construction equipment productivity using structural equation modeling," Buildings, vol. 13, no. 2, p. 502, 2023, doi: https://doi.org/10.3390/buildings13020502.
A. Maddeppungeng, S. Asyiah, D. E. Intari, B. I. Hakim, and D. N. Setiawati, "Analysis of Heavy Equipment Productivity Tower Crane in The Construction Project of Sultan Maulana Hasanudin State Islamic University Building," Fondasi : Jurnal Teknik Sipil, vol. 12, 2023, doi: https://dx.doi.org/10.36055/fondasi.v12i2.21982.
D. Hadiyatmoko, J. U. D. Hatmoko, and M. A. Wibowo, "Analysis of Launcher’s Productivity in Erection Girder Using Time Motion Study Method," Civil Engineering Journal, vol. 9, no. 8, pp. 1897-1911, 2023, doi: http://dx.doi.org/10.28991/CEJ-2023-09-08-06.
I. A. Ahmad and M. S. HS, "Analisis Produktivitas Dan Biaya Operasional Tower Crane Pada Proyek Puncak Central Business District Surabaya," Jurnal Rekayasa Teknik Sipil, vol. 2, no. 2, pp. 1-12, 2018. [Online]. Available: https://core.ac.uk/outputs/230737552/?utm_source=pdf&utm_medium=banner&utm_campaign=pdf-decoration-v1.
G. w. Subagyo and R. Tjondro, "Analisis Produktivitas Tower Crane (Studi Kasus Proyek Bintaro Jaya Xchange Tahap II, Tangerang Selatan)," Indonesian Journal Of Construction Engineering And Sustainable Development (CESD), vol. 4, 2021, doi: https://doi.org/10.25105/cesd.v4i2.12510.
E. Hasdian, M. A. Maulana, N. C. Fertilia, and Y. Lutfiansyah, "Analysis Comparissons of Ereciton Girder Implementations Methods Using Laucher Gantry and Crawler Crane Based on Cost and Time:(Case Study: Cimanggis-Cibitung Toll Road Project Section II Cibubur Area)," ADRI International Journal of Sciences, Engineering and Technology, vol. 6, no. 2, pp. 78-88, 2021. [Online]. Available: http://adri.journal.or.id/index.php/ijset/index.
A. Salsabila, R. T. Iriana, S. Djuniati, M. Sebayang, and E. Elianora, "Optimalisasi Penempatan Tower Crane Pada Proyek Pembangunan Gedung Pascasarjana, Universitas Riau," Jurnal Ilmiah Rekayasa Sipil, vol. 21, no. 2, pp. 253-265, 2024, doi: https://doi.org/10.30630/jirs.v21i2.1425.
S. M. Hastanto and F. Ratu Gudam, "Studi Kasus Perubahan Letak Dan Pondasi Tower Crane Static Menjadi Tower Crane Climbing Pada Proyek at District 8 Senopati Jakarta Selatan," Jurnal Forum Mekanika, vol. 5, no. 1, pp. 53-60, 2016 2016, doi: 10.33322/forummekanika.v5i1.641.
V. Mergl and J. Kašpárek, "Verifying the lifting and slewing dynamics of a harvester crane with possible levelling when operating on sloping grounds," Forests, vol. 13, no. 2, p. 357, 2022, doi: https://doi.org/10.3390/f13020357.
A. R. Umar and P. R. T. Naibaho, "Analisa Perbandingan Pelaksanaan Erection Girder Underpass pada Jalan Nasional dengan Metode Crane dan Metode Launcher," Asian Journal of Mechatronics and Electrical Engineering, vol. 1, no. 1, pp. 1-12, 2022, doi: https://doi.org/10.55927/ajmee.v1i1.1122.
E. N. Kulo, J. E. Waani, and O. H. Kaseke, "Analisa Produktivitas Alat Berat Untuk Pekerjaan Pembangunan Jalan (Studi Kasus: Proyek Pembangunan Jalan Lingkar SKPD Tahap 2 Lokasi Kecamatan Tutuyan Kabupaten Bolaang Mongondow Timur)," Jurnal Sipil Statik, vol. 1, no. 7, 2017, doi: Prefix 10.55927.
M. Indrayadi and R. Pratiwi, "Analisa Produktivitas Peralatan Konstruksi Pada Proyek Pembangunan Infrastruktur Universitas Tanjungpura (IDB)," JeLAST: Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang, vol. 5, no. 3, doi: https://doi.org/10.26418/jelast.v5i3.30317.

Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Massayu Sekar Bawana, Milinda Nur Indah Puspita, I Nyoman Dita Pahang Putra

This work is licensed under a Creative Commons Attribution 4.0 International License.