Structural Improvement Planning of Road Pavement with Modified Porous Asphalt Mixture using AASHTO 1993

Authors

  • Arief Aszharri Civil Engineering, Politeknik Negeri Sriwijaya, Indonesia
  • Dimas Ariezky Susetyo Civil Engineering, Politeknik Negeri Sriwijaya, Indonesia
  • Nadra Mutiara Sari Civil Engineering, Politeknik Negeri Sriwijaya, Indonesia

DOI:

https://doi.org/10.24036/cived.v12i1.688

Keywords:

Porous Asphalt, Overlay, Thick Pavement Layer, AC-WC

Abstract

The new technology that is being developed is porous asphalt pavement structures, which are made for road segments with less dense traffic. This structure is designed to include facilities such as parking lots, bicycle lanes, pedestrian sidewalks, and tennis court areas. This study involves the analysis of calculation results based on secondary field data and experimental data from laboratory-scale experiments. The design of the road pavement is based on the AASHTO 1993 method. The field data used includes information on the LHR (Load History Record) of the Dawuan Highway (Cikampek) section, the CBR (California Bearing Ratio) value of the subgrade, and the existing pavement conditions (including existing pavement structures and deflection data). Meanwhile, experimental data comes from testing the resilient modulus of porous asphalt mixtures using Cariphalte asphalt and additional gilsonite material with optimal levels. The resilient modulus value was obtained from laboratory testing using the Universal Material Testing Apparatus (UMATTA). The results of this study produced a pavement design using a gilsonite mixture that produced a thinner thickness than standard AC-WC materials. For example, for segment 3 with a modified mixture, the pavement thickness is 13 cm, while the standard AC-WC produces a thickness of 20 cm. It can be seen that using a modified Gilsonite mixture requires an overlay layer 7 cm thinner than using a standard AC-WC mixture.

Downloads

Download data is not yet available.

References

J. N’Cho, "Contribution of talent analytics in change management within project management organizations The case of the French aerospace sector," Procedia computer science, vol. 121, pp. 625-629, 2017, doi: https://doi.org/10.1016/j.procs.2017.11.082.

A. Nursin, F. Fitria, and T. W. Sari, "Last Planner System pada Proyek Rumah Susun Transit Oriented Development," in Prosiding Seminar Nasional Teknik Sipil, 2020, pp. 32-40. [Online]. Available:https://prosiding-old.pnj.ac.id/index.php/snts/article/download/3612/2038?__cf_chl_tk=YwJ8VDZUmMYEOGDySnLtQSk7btcYqadsrShaUVxaBi0-1735009117-1.0.1.1-8af8ylPgvvfTfFKwZxB.QjeS7OAFapkT0PEUsbg7F_0.

B. B. Kalengkongan, T. T. Arsjad, and J. B. Mangare, "Analisa Perhitungan Produktivitas Alat Berat Pada Pekerjaan Pematangan Lahan Pembangunan Tower Sutet Likupang-Paniki," Jurnal Sipil Statik, vol. 8, no. 1, 2020. [Online]. Available: https://ejournal.unsrat.ac.id/index.php/jss/article/view/27722/0.

A. Setiobudi, "Pengujian Kuat Tekan Beton Mutu Tinggi Type Fc’ 50 (Kelas Aa) Untuk Girder Jembatan Di Tol Palembang Indralaya (Palindra)," Jurnal Deformasi, vol. 2, no. 1, pp. 7-25, 2017, doi: https://doi.org/10.31851/deformasi.v2i1.1200.

D. Wijanarko and R. W. Rahmadi, "Optimalisasi Produksi Alat Berat Dalam Pekerjaan Galian Dan Tanaman Di Proyek Jalan Raya (Studi Kasus: Jalur Lintas Selatan Lot 2 Blitar)," Jurnal Daktilitas, vol. 4, no. 01, pp. 25-36, 2024. [Online]. Available: https://journal.unita.ac.id/index.php/daktilitas/article/view/1157/669.

S. S. Chandra, S. M. Sepasgozar, V. R. P. Kumar, A. K. Singh, L. Krishnaraj, and B. O. Awuzie, "Assessing factors affecting construction equipment productivity using structural equation modeling," Buildings, vol. 13, no. 2, p. 502, 2023, doi: https://doi.org/10.3390/buildings13020502.

A. Maddeppungeng, S. Asyiah, D. E. Intari, B. I. Hakim, and D. N. Setiawati, "Analysis of Heavy Equipment Productivity Tower Crane in The Construction Project of Sultan Maulana Hasanudin State Islamic University Building," Fondasi : Jurnal Teknik Sipil, vol. 12, 2023, doi: https://dx.doi.org/10.36055/fondasi.v12i2.21982.

D. Hadiyatmoko, J. U. D. Hatmoko, and M. A. Wibowo, "Analysis of Launcher’s Productivity in Erection Girder Using Time Motion Study Method," Civil Engineering Journal, vol. 9, no. 8, pp. 1897-1911, 2023, doi: http://dx.doi.org/10.28991/CEJ-2023-09-08-06.

I. A. Ahmad and M. S. HS, "Analisis Produktivitas Dan Biaya Operasional Tower Crane Pada Proyek Puncak Central Business District Surabaya," Jurnal Rekayasa Teknik Sipil, vol. 2, no. 2, pp. 1-12, 2018. [Online]. Available: https://core.ac.uk/outputs/230737552/?utm_source=pdf&utm_medium=banner&utm_campaign=pdf-decoration-v1.

G. w. Subagyo and R. Tjondro, "Analisis Produktivitas Tower Crane (Studi Kasus Proyek Bintaro Jaya Xchange Tahap II, Tangerang Selatan)," Indonesian Journal Of Construction Engineering And Sustainable Development (CESD), vol. 4, 2021, doi: https://doi.org/10.25105/cesd.v4i2.12510.

E. Hasdian, M. A. Maulana, N. C. Fertilia, and Y. Lutfiansyah, "Analysis Comparissons of Ereciton Girder Implementations Methods Using Laucher Gantry and Crawler Crane Based on Cost and Time:(Case Study: Cimanggis-Cibitung Toll Road Project Section II Cibubur Area)," ADRI International Journal of Sciences, Engineering and Technology, vol. 6, no. 2, pp. 78-88, 2021. [Online]. Available: http://adri.journal.or.id/index.php/ijset/index.

A. Salsabila, R. T. Iriana, S. Djuniati, M. Sebayang, and E. Elianora, "Optimalisasi Penempatan Tower Crane Pada Proyek Pembangunan Gedung Pascasarjana, Universitas Riau," Jurnal Ilmiah Rekayasa Sipil, vol. 21, no. 2, pp. 253-265, 2024, doi: https://doi.org/10.30630/jirs.v21i2.1425.

S. M. Hastanto and F. Ratu Gudam, "Studi Kasus Perubahan Letak Dan Pondasi Tower Crane Static Menjadi Tower Crane Climbing Pada Proyek at District 8 Senopati Jakarta Selatan," Jurnal Forum Mekanika, vol. 5, no. 1, pp. 53-60, 2016 2016, doi: 10.33322/forummekanika.v5i1.641.

V. Mergl and J. Kašpárek, "Verifying the lifting and slewing dynamics of a harvester crane with possible levelling when operating on sloping grounds," Forests, vol. 13, no. 2, p. 357, 2022, doi: https://doi.org/10.3390/f13020357.

A. R. Umar and P. R. T. Naibaho, "Analisa Perbandingan Pelaksanaan Erection Girder Underpass pada Jalan Nasional dengan Metode Crane dan Metode Launcher," Asian Journal of Mechatronics and Electrical Engineering, vol. 1, no. 1, pp. 1-12, 2022, doi: https://doi.org/10.55927/ajmee.v1i1.1122.

E. N. Kulo, J. E. Waani, and O. H. Kaseke, "Analisa Produktivitas Alat Berat Untuk Pekerjaan Pembangunan Jalan (Studi Kasus: Proyek Pembangunan Jalan Lingkar SKPD Tahap 2 Lokasi Kecamatan Tutuyan Kabupaten Bolaang Mongondow Timur)," Jurnal Sipil Statik, vol. 1, no. 7, 2017, doi: Prefix 10.55927.

M. Indrayadi and R. Pratiwi, "Analisa Produktivitas Peralatan Konstruksi Pada Proyek Pembangunan Infrastruktur Universitas Tanjungpura (IDB)," JeLAST: Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang, vol. 5, no. 3, doi: https://doi.org/10.26418/jelast.v5i3.30317

Downloads

Published

2025-03-28

How to Cite

Aszharri, A., Susetyo, D. A., & Sari, N. M. (2025). Structural Improvement Planning of Road Pavement with Modified Porous Asphalt Mixture using AASHTO 1993. CIVED, 12(1), 63–75. https://doi.org/10.24036/cived.v12i1.688

Issue

Section

Articles